Water Well #19

The District’s long awaited Water Well #19 Project began construction in May, 2014.  The project involved the construction of a new potable water well, water storage reservoir, booster pump, chlorination system and a pipeline connecting Well #12 to new water Well #19.  This project will also address the arsenic contamination at District Well #12 by blending water from Well #12 with water from Well #19.  Through their diligent efforts, the District’s Board of Directors was successful in obtaining funding through the State of California’s State Revolving Fund for the project, providing 80% of the project costs via the grant.  The project was under construction for approximately two years.  This project was completed in January, 2016.